Wirtschaftsnachrichten (Symbolbild).
Dienstag, 02.07.2019 13:01 von | Aufrufe: 156

Tinka Reports Positive PEA for the Ayawilca Zinc Project After-Tax NPV8% of US$363M and IRR of 27% Initial Capex of US$262M

Wirtschaftsnachrichten (Symbolbild). pixabay.com

PR Newswire

VANCOUVER, July 2, 2019 /PRNewswire/ - Tinka Resources Limited ("Tinka" or the "Company") (TSXV & BVL: TK) (OTCPK: TKRFF) is pleased to announce positive results from the Preliminary Economic Assessment ("PEA") prepared for its 100%-owned Ayawilca Zinc Zone project in central Peru. The PEA was prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101") by Amec Foster Wheeler Peru S.A. (Wood) as principal consultant, Transmin Metallurgical Consultants, and RPA Inc.  The PEA provides the initial economic assessment for an underground ramp-access mine development with a 5,000 tonnes per day processing plant.

PEA Highlights

  • After-tax NPV8% of US$363 million and pre-tax NPV8% of US$609 million using metal prices of US$1.20/lb zinc, US$18/oz silver, and US$0.95/lb lead on a 100% equity basis;
  • Initial Capex of US$262 million with after-tax IRR of 27.1% and pre-tax IRR of 37.2%;
  • 21-year mine life with average head grades of 6.05% zinc, 18.3 g/t silver, 67.1 g/t indium, and 0.25% lead;
  • Average annual production of approximately 101,000 tonnes of zinc recovered in concentrate and approximately 906,000 ounces of silver in a silver-lead concentrate;
  • Leverage to zinc price: 20% increase in zinc price increases after-tax NPV8% to US$606 million;
  • Numerous opportunities identified for potential economic improvement & exploration upside.

Note: The PEA is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the preliminary economic assessment will be realized.  Mineral resources are not mineral reserves and do not have demonstrated economic viability.

Tinka's President and CEO, Dr. Graham Carman, stated: "We are very pleased with the results of the PEA, which is based on a mid-sized underground mining case of 5,000 tonnes per day and relatively modest initial capital. The PEA shows that the Ayawilca Zinc project, which is located in one of the world´s most prolific polymetallic belts, is shaping up to be one of the best new zinc development projects in the Americas with strong economics and a long mine life of over 20 years.  The excellent PEA results are a major milestone and justify the continued advancement of Ayawilca towards production while exploration drilling is continuing with the aim of discovering additional high grade zinc resources." 

 Financial Summary

Pre-tax


ARIVA.DE Börsen-Geflüster

Kurse

0,0895
0,00%
Tinka Resources Realtime-Chart

After-tax

NPV (8% discount rate)

IRR

Payback period

US$609 million

37.2%

2.2 years

US$363 million

27.1%

3.1 years

Pre-production capital expenditure (Capex)1

Sustaining Capex

Life of Mine (LOM) Capex

Closure Cost (5.0% of LOM Capex)

US$261.9 million

US$144.6 million

US$406.5 million

US$20.3 million

Notes:

1 Includes contingencies of US$45 million.

 

Operating Summary


Processing plant throughput

Average annual zinc concentrate production

Average annual lead-silver concentrate production

Average annual silver in lead concentrate

Net Smelter Return from zinc and lead concentrates

5,000 t/day

201,500 dmt/year

7,570 dmt/year

905,700 oz/year

US$4,002 million

Mining costs

Processing costs

G&A costs

Total Operating Costs (Opex)

US$36.66/t

US$6.44/t

US$5.48/t

US$48.57/t

Notes:

dmt = dry metric tonne 

 

Metal Prices & Exchange Rate Assumptions

Input value

Zinc Price

Lead Price

Silver Price

NSR Cut-off value

Exchange Rate - Peruvian SOL/USD

US$1.20/lb

US$0.95/lb

US$18/oz

US$65/t

3.3

Total material processed (LOM)

38.2 million tonnes

Mine Life

21.1 years

 

PEA Mine Plan – 5,000 Tonnes per Day Underground Mining Operation

The PEA for the Ayawilca Zinc Zone is based on an underground mine operating at a mining rate of 5,000 tonnes per day for a mine life of 21.1 years.  For the purposes of the PEA, production is assumed to commence in 2023 following 18 months of construction and commissioning.  This initial mine plan is based on mining a total of 8.4 million tonnes Indicated Resources (grading 6.95% Zn, 0.18% Pb and 15.8 g/t Ag) plus 29.8 million tonnes Inferred Resources (grading 5.79% Zn, 0.27% Pb, and 19.0 g/t Ag) over the life of mine ("LOM") using an NSR cut-off value of US$65/t (of the 11.7 Mt Indicated and 45.0 Mt Inferred Resources at a US$55/t NSR cut-off value).  The zinc-rich mill feed will be trucked to the surface via a one-way-traffic ramp system connecting two mine portals to the underground infrastructure and accessing production areas starting at West and South Ayawilca.

Processing of the zinc mineralization will be through a standard crushing and grinding circuit followed by froth flotation, concentrate thickening and filtration.  The mine operation will produce two concentrates:  a zinc concentrate which is anticipated to assay 50% zinc based on metallurgical test work; and a lead concentrate which is anticipated to assay 50% lead and between 2,750 and 5,930 g/t silver (calculated on assays and based on similar base metal operations).  About half of the tailings will be thickened and sent to a surface tailings storage facility, while the remainder will be mixed with cement and used as structural backfill in the underground operations.

Based on preliminary mine plan analysis including resource geometry, the scale of the deposit and grade distribution, room and pillar ("R&P") and post-pillar mining ("P&P") methods were selected.

The estimated operating costs, over the life of the Project, are as follows:

Operating Costs per Mining Method (Opex)

Description

Cost per Tonne Processed

Mining – Room & Pillar

Mining – Post & Pillar

US$38.06

US$35.29

Average Mining Cost

Process Plant

G&A (US$10M/yr)

Total Operating Cost

US$36.66

US$6.44

US$5.48

US$48.58

 

The major components of the initial capital expenditures of US$261.9 million include US$76.3 million for the processing plant, US$34.3 million for on-site infrastructure, US$43.1 million for mine equipment and underground pre-production development, US$14.7 million for off-site infrastructure, and US$6.7 million for a starter tailings storage facility direct costs.  Contingencies in the capital costs total US$44.5 million.  The major components of sustaining capital are US$109.7 million for mining equipment and underground development, and US$34.9 million for tailings management over the 21.1 year mine life.

Capital Cost Item

Initial (US$ M)

Sustaining (US$ M)

Total (US$ M)

Mining & mine development

Process plant

On-site infrastructure

Off-site infrastructure

Tailings storage facility

Werbung

Mehr Nachrichten zur Tinka Resources Aktie kostenlos abonnieren

E-Mail-Adresse
Benachrichtigungen von ARIVA.DE
(Mit der Bestellung akzeptierst du die Datenschutzhinweise)

Hinweis: ARIVA.DE veröffentlicht in dieser Rubrik Analysen, Kolumnen und Nachrichten aus verschiedenen Quellen. Die ARIVA.DE AG ist nicht verantwortlich für Inhalte, die erkennbar von Dritten in den „News“-Bereich dieser Webseite eingestellt worden sind, und macht sich diese nicht zu Eigen. Diese Inhalte sind insbesondere durch eine entsprechende „von“-Kennzeichnung unterhalb der Artikelüberschrift und/oder durch den Link „Um den vollständigen Artikel zu lesen, klicken Sie bitte hier.“ erkennbar; verantwortlich für diese Inhalte ist allein der genannte Dritte.